Double Cross Delays

by James Brown

Well I guess it was inevitable that something would delay the completion of the pilot run today…..it turns out that due to some power outages at the transformer factory, we won’t receive the power and output transformers until sometime next week.

Secondly, the footswitch control circuit boards are also delayed.  In manufacturing, it only takes one missing component to prevent building something, but with two it’s even tougher to work around.  So we’ll have to postpone that final build.

As soon as we get the parts in, I will be completing the pilot run and I’ll post some pictures of that assembly process. 

In the meantime, I just uploaded a draft version of the owners manual to the regular location on kustom.com:

Double Cross Owners Manual

Thanks,

James

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.